Unsung heroes: Two hurricanes couldn't stop this project team

Building Team Awards

Unsung heroes: Two hurricanes couldn't stop this project team

Bronze Award: St. Lucie County’s population exploded to the point where the hospital needed lots more space.


By Robert Cassidy, Executive Editor | June 19, 2019

Three 45,000-sf floors were added above the existing hospital, along with a new ED, ED observation unit, and PACU. Photos: Ben Tanner

One hurricane would test most project teams. But a Building Team led by construction manager Robins & Morton had to battle through both Hurricane Matthew in 2016 and Hurricane Irma in 2017 to complete the 164,000-sf expansion of Tradition Medical Center, Port Saint Lucie, Fla.

Martin Health System had wisely built the original three-story hospital, which opened in 2013, with enough structural capacity for vertical expansion. In less than two years, St. Lucie County’s population had exploded to the point where the hospital needed lots more space.

Robins & Morton, HKS (architect), and TLC Engineering for Architecture (SE/MEP) used an owner-inspired hybrid IPD delivery model and Lean techniques to add three 45,000-sf floors and a penthouse directly above the neonatal intensive care unit and labor delivery department. They spent a year with the maternity and NICU nurses planning two perfect relocations of the babies—four moves in all—during construction.

 

 

Two horizontal additions provided room for a two-story emergency department, an 18-bed ED observation unit, a second-floor post-anesthesia care unit, a materials handling facility, and a 10,000-sf data center that the owner added to the original project scope. They also found ways to spend an extra $4 million on a new catheter lab.

To overcome labor shortages, the team used prefabricated headwalls and shower basins and built MEP racks, ductwork, medical gas piping, heat and hot water piping, and chilled water piping off site. These were formed into 20-foot runs ready for assembly and connection on site.

Incidentally, after securing the open structure ahead of Hurricane Matthew, several Robins & Morton staff stayed on at the hospital—on their own time—to safeguard patients and hospital staff. “They were unsung heroes,” said Matt Kelly, Director of Planning, Construction and Real Estate for Martin Health System.+

 

Building Team — Submitting firm Robins & Morton (CM), Owner Martin Health System, Owner’s representative CBRE, Architect HKS, SE/MEP engineer TLC Engineering for Architecture

General information — Cost $77 million, Size 164,000 sf, Construction time September 2015 to March 2018, Delivery method CM at risk

 

Return to the Building Team Awards landing page

Related Stories

| Aug 29, 2022

Montana becomes first U.S. state to approve 3D printing in construction

Montana is the first U.S. state to give broad regulatory approval for 3D printing in building construction.

Architects | Apr 22, 2022

Top 10 green building projects for 2022

The American Institute of Architects' Committee on the Environment (COTE) has announced its COTE Top Ten Awards for significant achievements in advancing climate action.

Concrete Technology | Apr 19, 2022

SGH’s Applied Science & Research Center achieves ISO 17025 accreditation for concrete testing procedures

Simpson Gumpertz & Heger’s (SGH) Applied Science & Research Center recently received ISO/IEC17025 accreditation from the American Association for Laboratory Accreditation (A2LA) for several concrete testing methods.

2021 Building Team Awards | Jan 14, 2022

First public-private partnership project in Veterans Administration history saves $34 million in costs

LEO A DALY and McCarthy Building Companies head the project team for the Omaha VA Ambulatory Care Center in BD+C’s 2021 Building Team Awards.

Building Team Awards | Dec 8, 2021

A performing arts center celebrates a legendary rocker and his birthplace

Buddy Holly Hall in Texas receives BD+C’s Silver Building Team Award.

Building Team Awards | Dec 7, 2021

A rapid response to a health emergency

Baptist Hospital of Miami’s 233-bed Hope Tower receives BD+C’s Bronze Building Team Award

Building Team Awards | Dec 3, 2021

Putting science on display, thanks to a design-build approach

UC Riverside’s Plant Growth Environments Facility receives BD+C’s Bronze Building Team Award.

Building Team Awards | Dec 2, 2021

An academic ‘precinct’ brings arts and sciences together

Wofford College’s Chandler Center for Environmental Studies receives BD+C’s Silver Building Team Award.

Building Team Awards | Dec 1, 2021

Denver sets the bar for water reclamation and reuse

A new administration building for the city’s water utility company scores Platinum in BD+C’s 2021 Building Team Awards.

2021 Building Team Awards | Nov 17, 2021

Caltech's new neuroscience building unites scientists, engineers to master the human brain

The Tianqiao and Chrissy Chen Institute for Neuroscience at the California Institute of Technology in Pasadena wins a Gold Award in BD+C's 2021 Building Team Awards.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021